{domain:"www.qualitydigest.com",server:"169.47.211.87"} Skip to main content

        
User account menu
Main navigation
  • Topics
    • Customer Care
    • Regulated Industries
    • Research & Tech
    • Quality Improvement Tools
    • People Management
    • Metrology
    • Manufacturing
    • Roadshow
    • QMS & Standards
    • Statistical Methods
    • Resource Management
  • Videos/Webinars
    • All videos
    • Product Demos
    • Webinars
  • Advertise
    • Advertise
    • Submit B2B Press Release
    • Write for us
  • Metrology Hub
  • Training
  • Subscribe
  • Log in
Mobile Menu
  • Home
  • Topics
    • Customer Care
    • Regulated Industries
    • Research & Tech
    • Quality Improvement Tools
    • People Management
    • Metrology
    • Manufacturing
    • Roadshow
    • QMS & Standards
    • Statistical Methods
    • Supply Chain
    • Resource Management
  • Login / Subscribe
  • More...
    • All Features
    • All News
    • All Videos
    • Training

Fluor Joint Venture Reaches Substantial Completion Stage

Chicago Transit Authority’s Red and Purple line project

Quality Digest
Bio
Mon, 07/20/2026 - 12:02
  • Comment
  • RSS

Social Sharing block

  • Print
Body

(Fluor Corp.: Irving, TX) -- Fluor Corp. and its joint venture partner, Walsh Construction Co., reached Substantial Completion on the Chicago Transit Authority’s (CTA) $2.1 billion Red and Purple Line Modernization (RPM) Phase One Project, the largest completed capital project in CTA’s history.

ADVERTISEMENT

The recently achieved milestone reflects the dedication and collaboration of an exceptional project team, including Fluor, Walsh Construction, Stantec (design), Hitachi (signaling), and Meade (electrical contractor).

“Reaching Substantial Completion on this landmark project is a testament to the strength of our partnerships, the commitment of our teams, and our shared focus on delivering transformational infrastructure,” says Shawn West, president of Fluor’s infrastructure business. “The RPM Phase One project will have a lasting impact on Chicago’s transit system and the communities it serves. I could not be more proud of what this team has accomplished.”

Since commencing in 2019, the program has modernized and replaced more than two miles of 100-year-old elevated track between Lawrence and Bryn Mawr, and rebuilt four stations into modern, fully accessible facilities with enhanced passenger flow, security, and signage. The project also includes the Red-Purple Bypass, a new elevated bypass for the Brown Line that eliminates track conflicts and improves throughput for Red, Purple, and Brown Line service. In addition, 11 miles of new digital track circuit signaling have been installed, increasing capacity today while enabling future enhancements in signaling and rolling stock.

The project was executed while maintaining rail transit service along the alignment. The new stations and tracks fully opened in the summer of 2025, with final completion for RPM Phase One set for November 2026.


With the Chicago skyline in the distance, a CTA Brown Line train travels on the new Red-Purple Bypass at the Belmont Station crossing. The elevated bypass eliminates track conflicts and improves throughput for Red, Purple and Brown line service.

Add new comment

The content of this field is kept private and will not be shown publicly.
About text formats
Image CAPTCHA
Enter the characters shown in the image.

© 2026 Quality Digest. Copyright on content held by Quality Digest or by individual authors. Contact Quality Digest for reprint information.
“Quality Digest" is a trademark owned by Quality Circle Institute Inc.

footer
  • Home
  • Print QD: 1995-2008
  • Print QD: 2008-2009
  • Videos
  • Privacy Policy
  • Write for us
footer second menu
  • Subscribe to Quality Digest
  • About Us