Any body know what the objectives of auditing conducted on Project Close-out event ?
Do we need this audit, because i think this audit does not have benefit to much, because the Corrective Action or Improvement will not help the Project Performance.
Regard's
D'Art.
Sign In to get started!
Comments
hershal 10/21/2002
Thomas,
The ISO 9001:2000 version section for internal audits (8.2.2) is nearly unchaged from ISO 9001:1994 clause 4.17....which means the requirements should be mostly unchanged. When I was at Newport Corporation, I was in the process of trying to get my auditors IRCA certifed. I was, and one other got certified, and had others in varying stages of progress. I recommend for internals that do not have potential for international exposure (in an audit role) either ASQ or RAB certification. For any that have the potential for international, then I recommend IRCA certification.
If you want a bit more info, chat with me directly.
Hershal
hershal_brewer@hotmail.com
562-699-0543 x3222